Set the evidence plan
Define what the pilot must prove, who approves the result, and which tests or documents are required before release.
Lithium Battery Company · OEM Battery Programs
Pilot battery builds designed to expose production risks, confirm acceptance criteria, and create an evidence-based release decision.
An OEM battery pilot build should prove that the approved pack can be produced repeatedly—not merely that one sample works. The pilot should test the design package, material controls, assembly process, firmware, inspection points, functional testing, documentation, packaging, and the production assumptions needed for the next release.
Catalog reference-design programs begin at 10 units and custom programs begin at 25 units. LBC does not quote individual retail battery orders.
Define what the pilot must prove, who approves the result, and which tests or documents are required before release.
Use the intended materials, process, test methods, and production partner while recording approved deviations and results.
Close critical findings, update the controlled package, and approve the next lot only when the evidence supports it.
There is no universal number. The lot must be large enough to evaluate the intended process and risks. LBC custom programs begin at 25 units, and the final pilot quantity is set by the program's evidence needs.
No. A pilot can support validation and certification planning, but required third-party testing and approvals remain specific to the product, market, shipping mode, and customer contract.
Usually, yes, when the goal is to qualify the production process. If an earlier engineering partner builds samples, a separate production-intent pilot may still be required.
The issue should be documented, contained, traced to its cause, and resolved through an approved design or process change before the affected requirement is released.